GlobalFoundries Mechanical Contract

Due to previous performance excellence at the Malta campus, Danforth was selected to be a member of the Cub-D CPD (Collaborative Project Delivery) Team. Working in collaboration with the design team, Danforth assisted in a fast-track design development of the HVAC Piping & Ductwork, Process Ductwork and Plumbing systems for the D-Cub project. The D-Cub will be a 100,000 ft mechanical support building providing facility utility requirements of the TDC building.

The CPD Team successfully set new standards for speed to delivery of Issued for Construction (IFC) documents, which were accompanied by a clash-free model, providing the opportunity to move immediately into fabrication and construction. This form of project delivery gave the owner an opportunity for a 4-month schedule gain.

Current project highlights include:

  • 26 days from start of BIM to start of fabrication
  • 58 days from start of BIM to start of installation
  • Unique installation of mechanical systems in parallel with structural installation, resulting in a 75% reduction of field welds

GlobalFoundries D-Cub Semiconductor Project Case Study (321 KB)

GlobalFoundries D-Cub Semiconductor Project Case Study (321 KB)

GlobalFoundries D-Cub Semiconductor Project Case Study GlobalFoundries D-Cub Project This case study outlines work done at GlobalFoundries’s D-Cub mechanical support building, showcasing Danforth’s Sheet Metal and Piping Fabrication and Installation.

GlobalFoundries D-Cub Semiconductor Project Case Study (321 KB)